Work is proceeding very rapidly on Newcom Student Union. Just three months remain before the point of substantial completion. Here are some highlights of current progress:

  • The structural steel is complete.
  • The installation of the roof sections over the additions to the building are nearly complete.
  • The large air handlers that will provide fresh air to the building have been installed on the roof.
  • The concrete floors have been poured inside the building.
  • Temporary heat has been installed to allow the finish work inside the building to continue.
  • Wall framing inside the building is substantially complete, and the installation of door frames is beginning.
  • Repair to the existing exterior masonry is underway, and the installation of the new masonry will begin soon.
  • Connecting the building water supply and sanitary sewer system will be completed in the next two weeks. This will include trenching outside of the construction fence area.
  • Plans are beginning to be developed for the move back into the building.

 

Outside view of Newcom Student Union construction  Inside view of Newcom Student Union construction  Inside view of Newcom Student Union construction  Inside view looking out of Newcom Student Union construction  Inside view looking out of Newcom Student Union construction  Inside view of Newcom Student Union construction